I haven’t been very good about updating the build log lately, but I HAVE been making a lot of progress:

  1. The spar is installed, and all reinforcing layups on and around it are complete.
  2. The upper firewall is installed, and the engine mount hard point reinforcements are complete.
  3. The turtleback is installed, and most of its reinforcements are in place.
  4. The canopy is in progress. It’s in place and trimmed, and the first UNI layup around its bottom lip is installed.

Progress may start to slow down now. The shop is definitely getting very cold, and it’s getting really hard to do work. Hopefully another propane heater will help – we have one right now, but it’s just barely keeping up.